Skip to content
New issue

Have a question about this project? Sign up for a free GitHub account to open an issue and contact its maintainers and the community.

By clicking “Sign up for GitHub”, you agree to our terms of service and privacy statement. We’ll occasionally send you account related emails.

Already on GitHub? Sign in to your account

Lab space expansion #21

Open
moorepants opened this issue Sep 26, 2024 · 1 comment
Open

Lab space expansion #21

moorepants opened this issue Sep 26, 2024 · 1 comment

Comments

@moorepants
Copy link
Contributor

Jason sent an email to Theo on September 25, 2024 with these final points:

  • Can the second electrical pole in the middle of the floor be removed or replaced with a floor outlet? The workers installed new wall outlets so that is sufficient.
  • There are three large holes in the floor, one in the new space and two in the old space. WIll these be filled?
  • There is no base/skirting board on one side of the opening to the new space. WIll that be added? The column could also probably use baseboard, to prevent it being beat up.
  • The wiring for the fire alarm still needs to be tidied up.
  • There is a large fire extinguisher, is that the construction workers? Or does it stay in the lab?
  • The ceiling panel by the new duct work in the old space is still exposed. Will that be fixed?
@moorepants
Copy link
Contributor Author

Theo's response:

Item 1, Electric column in the middle of the floor remove

  • C24091844-01 (call) created, follow-up I will again keep you informed.

Item 2, spar rings in the floor (1 in the expansion and 2 in the existing bike lab)

  • action merged to C24091844-01 , follow-up I will again keep you informed.

Item 3, Floor finish of the columns and under the radiator

  • C240918470, I want to have it included if Guido Hellemons agrees on the floor including structural ceiling.

Item 4, Fire alarm wiring.

Are we still working from the project, preparation present.

Point 5, Fire extinguisher

Can be hung in the room by the handyman, bracket is already present, just make a call for FM incl. location

Item 6, Finishing architectural ceiling due to new piping.

Passed on to the OC2 to finish this. Will be done by them.