📅 Date: 22/03/2023
📍 Location: CMPE Lounge
🕐 Duration: 1h 15m
📝 Note Taker: Leyla yayladere
👥 Attendees:
- Ahmed Bera Pay
- Ahmet Abdullah Susuz
- Ali Mert Geben
- Arda Arslan
- Hakan Emre Aktaş
- Leyla Yayladere
- Mehmet Süzer
- Rafet Oğuz Pançuk
- Ömer Şükrü Uyduran
- Ufuk Altunbulak
- Zülal Molla
- Reviewing prepared Requirements, Mock-ups and Scenarios as a whole team since these tasks are split into sub-groups
- Discussing any unclear points of requirements and how to proceed with them
- Discussing the use of Figma to improve our mock-ups and prepare them for mobile
- Everybody in the meeting became familiar with details of Requirements, Mock-ups and Scenarios.
- Everybody shared their ideas about Requirements, Mock-ups and Scenarios, and discussed any unclear points.
- Notification requirements were improved, but there were still some unclear parts. Decided to ask to PO.
- Decided that Mock-up design is sufficient for this stage and improving UI design is not necessary at this point.
- Decided that Mock-ups for mobile can be done with same platform, draw.io.
None until PO meeting
- date: 24/03/2023
- agenda: Validation of mock-ups and scenarios with PO
🏠 Home
- Hakan Emre Aktas
- Ahmed Bera Pay
- Ömer Şükrü Uyduran
- Mehmet Süzer
- Ahmet Abdullah Susuz
- Ali Mert Geben
- Oğuz Pançuk
- Arda Arslan
- Zülal Molla
- Leyla Yayladere
- Omer Faruk Unal
- Bengisu Kübra Takkin
451 Weekly Progress Reports
- Progress Report #1 | 03.10.2023
- Progress Report #2 | 10.10.2023
- Progress Report #3 | 17.10.2023
- Progress Report #4 | 24.10.2023
- Progress Report #5 | 07.11.2023
- Progress Report #6 | 14.11.2023
- Progress Report #7 | 21.11.2023
- Progress Report #8 | 05.12.2023
- Progress Report #9 | 12.12.2023
- Progress Report #10 | 19.12.2023
352 Meeting Notes
- Meeting #1 | 08.03.2023
- Meeting #2 | 13.03.2023
- Meeting #3 | 15.03.2023
- Meeting #4 | 22.03.2023
- Meeting #5 | 24.03.2023
- Meeting #6 | 30.03.2023
- Meeting #7 | 05.04.2023
- Meeting #8 | 07.04.2023
- Meeting #9 | 19.04.2023
- Meeting #10 | 27.04.2023
- Meeting #11 | 03.05.2023
- Meeting #12 | 06.05.2023
- Meeting #13 | 08.05.2023
- Meeting #14 | 10.05.2023
- CmpE451 Customer Milestone 1 Report
- CmpE451 Customer Milestone 2 Report
- CmpE451 Final Milestone Report