Milestone - October 15
Past due by about 1 month
75% complete
- Start design document, if not started, with considerable progress:
-
- Class diagram
-
- Use case diagram
-
- Sequence diagrams
- Plan for the presentation next week
- Prepare a lab report documenting what's done during the lab on Wiki
- Start design document, if not started, with considerable progress:
-
- Class diagram
-
- Use case diagram
-
- Sequence diagrams
- Plan for the presentation next week
- Prepare a lab report documenting what's done during the lab on Wiki