Notifications
You must be signed in to change notification settings - Fork 0
Commit
This commit does not belong to any branch on this repository, and may belong to a fork outside of the repository.
- Loading branch information
Showing
6 changed files
with
141 additions
and
2 deletions.
There are no files selected for viewing
This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
Original file line number | Diff line number | Diff line change |
---|---|---|
@@ -1,2 +1,121 @@ | ||
# cylc-7-8-sched-comp | ||
A simple documented example comparing the Cylc 7 and 8 scheduling algorithms. | ||
# Cylc 7 vs 8 Scheduling Comparison | ||
|
||
Note: I've glossed over many details here in the interests of clarity. | ||
|
||
## Cylc 7 Scheduling Algorithm (simplified) | ||
|
||
Cylc 7 initializes its *task pool* with a *waiting* instance of every task | ||
at the first cycle point. Those with no prerequisites can submit immediately. | ||
|
||
When a task (e.g. `a.1`) submits, the scheduler spawns its next-cycle | ||
instance (`a.2`) as *waiting*. | ||
|
||
When a task completes an output, the scheduler matches completed outputs | ||
with unsatisfied prerequisites across the task pool to see if other | ||
tasks become ready. | ||
|
||
*Succeeded* tasks can be dropped from the pool once there are no *waiting* | ||
tasks left that they could potentially satisfy (roughly, no waiting tasks | ||
remaining in the same cycle point). | ||
|
||
*So Cylc 7 extends the workflow by spawning the next instance of each task | ||
at submit time, not by following the graph! The pre-spawned tasks do then | ||
run according to the dependencies, however.* | ||
|
||
## Cylc 8 Scheduling Algorithm (simplified) | ||
|
||
The dependency graph is a network of `parent => child` relationships. Cylc 8 | ||
initializes its task pool with a waiting instance of every parentless task, | ||
out to the runahead limit. These can all submit immediately (no prerequisites). | ||
|
||
Whenever a task completes an output the scheduler spawns the associated | ||
downstream child "on demand" (so unused branches do not get spawned at all). | ||
|
||
*Cylc 8 evolves and runs the graph purely according to the dependencies.* | ||
This is conceptually much simpler than Cylc 7 algorithm and solves all of its | ||
problems - see below. | ||
|
||
----------- | ||
|
||
## Example | ||
|
||
### Time Zero (start up) | ||
|
||
 | ||
|
||
Cylc 7 starts with the first instance of every task. | ||
|
||
Cylc 8 starts with just the parentless tasks at the top of each cycle | ||
|
||
If the graph had 1000 tasks downstream of `x` the Cylc 7 task pool would | ||
initially number 1001, but Cylc 8 would still have just 3 tasks. | ||
|
||
### Time One (later) | ||
|
||
 | ||
|
||
The Cylc 7 task pool expands across active cycle points. It may contain up | ||
to N times the number of tasks per cycle, where N is the number of cycles. | ||
|
||
The Cylc 8 task pool is typically far smaller and is not affected by spread | ||
over active cycle points. | ||
|
||
### Time Two (later again) | ||
|
||
 | ||
|
||
The Cylc 7 task pool continues to grow as the active cycle points fill out. | ||
The scheduler can't clear out cycle 1 until no waiting tasks remain there. | ||
|
||
Note the content of the Cylc 7 task pool can't be explained without | ||
understanding the scheduling algorithm. | ||
|
||
The Cylc 8 pool is easily explained: there are 3 active tasks (obvious) and | ||
one waiting (spawned by `1/b:succeeded`, still waiting on `1/c:succeeded`). | ||
|
||
------------- | ||
|
||
## Interventions: Matching and Operating on Tasks | ||
|
||
### Cylc 7 | ||
|
||
In Cylc 7 you can only match and operate on tasks that remain in the task pool. | ||
Beyond that you must first *insert* tasks into the pool. | ||
|
||
To rerun a sub-graph in Cylc 7 you have to "reset" existing (pool) sub-graph | ||
members to waiting and insert any ex-pool members, to set up the re-run before | ||
triggering the initial tasks. | ||
|
||
However, in clock-limited workflows the bloated Cylc 7 pool makes it likely | ||
that "all the tasks" remain in the pool for the current cycle, which makes | ||
many interventions easier than one might expect for this model. | ||
|
||
### Cylc 8 | ||
|
||
In Cylc 8 you can operate on individual tasks anywhere in the infinite graph, | ||
and downstream consequences will flow naturally with no pre-setup (reset or | ||
insert) required. | ||
|
||
However, matching tasks by glob or family name currently (Cylc 8.3.0) only works | ||
in the task pool. This is just like Cylc 7, but the much leaner pool (e.g. no | ||
succeeded tasks in the Cylc 8 pool) can make some mass interventions more | ||
involved than for Cylc 7, e.g. to target individual family members. This will | ||
become much easier soon though, in future releases. | ||
|
||
------------- | ||
|
||
## What You See in the GUI | ||
|
||
### Cylc 7 | ||
|
||
The Cylc 7 GUI shows only the current task pool, end of story. However, the | ||
task pool is bloated and it is likely that "all the tasks" remain in the | ||
current cycle of real-time clock-triggered workflows. | ||
|
||
### Cylc 8 | ||
|
||
The Cylc 8 GUI shows (in all views) a configurable graph-based window around | ||
the much leaner task pool. The default `n=1` window shows all tasks out to 1 | ||
graph edge from the (`n=0`) task pool. | ||
|
||
How much of the workflow you see in the Cylc 8 GUI is just a choice. |
This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
Original file line number | Diff line number | Diff line change |
---|---|---|
@@ -0,0 +1,10 @@ | ||
[scheduler] | ||
allow implicit tasks = True | ||
[scheduling] | ||
cycling mode = integer | ||
[[graph]] | ||
P1 = """ | ||
x => a | ||
a[-P1] => a | ||
a => b & c => y | ||
""" |
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
Original file line number | Diff line number | Diff line change |
---|---|---|
@@ -0,0 +1,10 @@ | ||
## Simplifying assumptions in this example | ||
|
||
- skipping over the *submitted* task state | ||
- no queues etc. that put more waiting tasks in the pool | ||
- all dependencies are of the form `a:succeeded => b` | ||
- only one cycling sequence in the graph | ||
- no external triggers (including clock triggers) | ||
- the runahead limit is 3 (or more) cycle points | ||
- runahead-limited task instances are omitted | ||
- tasks complete all their outputs successfully |